Job 0119 / 0132 | June 2023
“From design to completion of the distribution equipment we found the team to be very accommodating. The complete distribution equipment package was successfully delivered on time, and we look forward to working on future projects together.”
James Field, Electrical Contracts Manager, Neptune Building Services
We won this contract to supply the entire electrical distribution infrastructure from the 2500A rated Main Switchboard through to 2 MCCB sub distribution panelboards and 18 final circuit MCB distribution boards. The value of this project was more than £110,000.
Supply included delivery to site with offloading and location of the large multi sectional switchgear. Our engineers moved the individual sections with our specialist moving/lifting equipment into their final location. Once in position these sections needed to have all the internal busbar joints installed with the finished switchboard being Insulation and Flash Tested @ 2500V.
A bespoke 2500A generator connection chamber box was also designed for this project. We manufactured customer copper connections and Tufnol support bars to accommodate numerous electrical connections per phase. The copper connections were 100x10mm laminations and the cable connections were 400mm. A polycarbonate protetice screen was also cut and bent to protect the end of line user.
The larger sub distribution panelboards had to accommodate extremely large sub mains cabling. Again, custom made coppers were required to terminate these cables. All made in house to suit.